Site Details
Contractor: TSL Construction Ltd
Development Consultant: Macdonald & Cameron Ltd
Employer’s Agent: Pick Everard Anticipated
Site Start: July 2026
Anticipated Completion: Autumn 2027
Number of Homes:
12 x 2 Bed 4 person flats for affordable social rent.
4 x 3 Bed 6 person semi-detached homes for affordable social rent.
2 x 4 Bed 6 person semi-detached homes for affordable social rent.
Latest Update
February 2026: TSL Construction Ltd has been selected as the preferred contractor for the Glenkingie Terrace development in Caol, following a competitive tender process.
A site start was achieved in July 2025, and TSL Construction Ltd has erected the first timber kit homes and flats for the development. Internally, the furthest advanced units have cabling, pipework and plasterboard installed, ready for finishings (for example kitchens and bathroom fittings) to progress.
Externally, the tar has been laid for the main road, with road widening works progressing.
The new homes are expected to be completed by Spring 2027.