Rankin Crescent Phase 2, Lochyside

Site Details

Contactor and Principal Designer: R.E. Campbell
Development Consultant: MacDonald & Cameron Ltd
Employer’s Agent: Pick Everard, Inverness
Site start date: 20th November 2023
Anticipated Completion: April 2026
Number of Homes:
8 x 2 Bed 4 person semi-detached homes for affordable social rent.
10 x 3 Bed 6 person semi-detached homes for affordable social rent. 
4 x 2 Bed 4 person semi-detached homes for New Supply Shared Equity.

Latest Update

June 2025. The Rankin Crescent development in Lochyside is progressing well, with kitchens and bathrooms having been installed in the most advanced homes, and final decoration and roughcasting works to begin shortly.

Site infrastructure works are well underway, and the development remains on track for completion in April 2026.

Rankin Crescent1 Feb 2025

Rankin Crescent2 Feb 2025

Rankin Crescent1 Jul 24

Rankin Crescent3 Jul 24

Rankin Crescent4 Jul 24