Site Details

Contactor and Principal Designer: R.E. Campbell
Development Consultant: Macdonald & Cameron Ltd
Employer’s Agent: Pick Everard, Inverness
Site start date: 20th November 2023
Anticipated Completion: April 2026
Number of Homes:
8 x 2 Bed 4 person semi-detached homes for affordable social rent.
10 x 3 Bed 6 person semi-detached homes for affordable social rent. 
4 x 2 Bed 4 person semi-detached homes for New Supply Shared Equity.

Latest Update

September 2025: The Rankin Crescent development in Lochyside is progressing well, with kitchens, bathrooms and final coat decoration having been undertaken in the most advanced homes. Externally, roughcasting and painting work is complete to the majority of the new homes, and the gardens for the development are being formed.

Site infrastructure works are well underway, and the development remains on track for completion by April 2026.